Bourne Place March Update
Following the last newsletter update from our construction team, PDR, we would like to update on the progress of the Bourne Place leisure quarter.

There has been significant progress made since the beginning of the year, with the initial stages of the building envelope now in place, following the completion of the piling stage in January.

Foundation works on the cinema building are nearing completion, and PDR anticipate that the steel frame construction will be complete within six to eight weeks.

The next critical stage of works is the erection of the lightweight steel frame for the hotel, and the delivery of the modular bathroom pods, which is likely to begin towards the end of March.

PDR are part of the Considerate Constructors Scheme, and are committed to ensuring the safety and welfare of the public and others surrounding the site. They have been working to ensure the cleanliness of the surronding roads and pavements.

If you have any queries regarding the Spirit of Sittingbourne scheme, get in touch by emailing info@spiritofsittingbourne.com