PDR Construction, who are building the Bourne Place leisure quarter, have released a quarterly update.

Further to our last newsletter issued in March 2019 we would like to provide the following update on the progress of your new Hotel, Eight Screen Cinema and associated Retail Units.

You will have no doubt noticed the substantial increase in site activity since the last update and we now have all the main steel structure complete to both the Hotel and the Cinema. 

You may have also noticed that we now have a large tower crane erected in the middle of the site which allows us to manage deliveries more efficiently and assists with easing traffic congestion in and around the site. This is now in regular use on both buildings.     

We have also started to commence external and internal finishes to the Hotel building and the bedroom areas are now starting to take shape along with external cladding and installation of the windows.

Similarly with the Cinema, external cladding is now progressing and we have recently commenced internal partitioning works now that the floor decks are complete.

Bricklaying has also commenced and you can now see progress with the individual retail units on the ground floor area to both buildings. All the concrete floors have now been poured on all levels.  

As noted above the site is now getting extremely busy with different trades and it is likely to get even busier within the next three / four months. The amount of site traffic entering and exiting the site is also likely to increase and this too is being closely managed and monitored to provide minimum disruption and disturbance to pedestrian and vehicular traffic.       

The health, safety and welfare of the public and others surrounding the site continues to be closely monitored as does the cleanliness of roads and pavements around the periphery of the development.

Kind Regards,

PDR Construction Limited